Downtown asphalt overlay set to begin September 7

Rogers Group will begin asphalt milling and paving operations in downtown Conway starting Sunday, September 7 at 6:00 p.m. While some work will take place during the day, most of the work will be completed during the evening hours through September 16.

Street parking will not be allowed for the dates listed below.

Milling – Beginning September 7 around 6:00 p.m.

  • September 7 – Main St – Harkrider St to Front St
  • September 8 – Chestnut St – College Ave to Main St
  • September 9 – Chestnut St – Main St to Oak St
  • September 9 – Front St – Spruce St to Smith St
  • September 10 – Front St – Smith St to Prairie St
  • September 11 – Locust Ave – College Ave to Robinson Ave
  • September 15 – Parkway Ave – Prince St to Mill St

Paving – Beginning September 7 around 8:00 p.m.

  • September 7 – Main St – Harkrider St to Chestnut St
  • September 8 – Main St – Chestnut St to Front St
  • September 8 – Chestnut St – College Ave to Prairie St
  • September 9 – Chestnut St – Prince St to Oak St
  • September 10 – Front St – Spruce St to Van Rankle St
  • September 11 – Front St – Van Rankle St to Prairie St
  • September 15 – Locust Ave – College Ave to Robinson Ave
  • September 16 – Parkway St – Prince St to Mill St